When you buy a new home or condo from an Ontario builder, your agreement must include a Tarion addendum, and its first page is the Statement of Critical Dates. That page is easy to skim past, but it decides how long the builder can delay your closing (for a freehold home) or occupancy (for a condo unit), how much notice you must be given, and when you can walk away with your money back. This guide summarises the rules as Tarion describes them. Always read your own addendum and confirm the details with your lawyer, because the dates in your agreement are what count.
Tentative dates vs. firm dates
A builder can sell with either a firm date or tentative dates.
- Firm Closing Date (freehold) or Firm Occupancy Date (condo): the date the builder commits to. If it is missed, the builder must set a delayed date and you are generally entitled to compensation.
- Tentative dates: common on pre-construction because the builder does not yet know exactly when the home will be finished. The builder sets a First Tentative date and can later move to further dates by giving proper notice, until a firm date is fixed.
- Outside Closing Date or Outside Occupancy Date: the latest date in the agreement. If the home is not ready by then, you get the right to end the agreement.
How the freehold timeline works
For freehold homes sold with tentative dates, Tarion describes a set sequence. The First Tentative Closing Date is the builder’s estimate. The Second Tentative Closing Date can be up to 120 days after the first, and the Firm Closing Date can be up to 240 days after the first. The Outside Closing Date is 365 days after the earlier of the second tentative date and the firm date. Each of these must be a business day and must be an actual calendar date rather than a “floating” date tied to some other event.
How the condo occupancy timeline works
For condo units the structure is similar but uses occupancy dates, because you usually move in before the building is registered and the purchase finally closes. The builder can set tentative occupancy dates and must set a final tentative or firm occupancy date by notice, including a step that ties to the completion of the roof. The firm date cannot fall after the Outside Occupancy Date in your agreement. If you are new to the difference between moving in and final closing, read interim occupancy in Ontario condos.
The 90-day notice rule
As a general rule, a builder must give at least 90 days’ written notice to change a closing or occupancy date. If the builder wants to move past the First Tentative date, notice must be given no later than 90 days before that date. On a freehold tentative-date agreement, Tarion explains that if proper notice is not given, the First Tentative Closing Date becomes the Firm Closing Date. That is why it matters to note every critical date in your calendar as soon as you sign.
There is also a short-notice rule. If a builder fails to give at least 10 days’ notice of a delay, Tarion sets a fixed payment of $1,500 (ten days at $150 a day).
What compensation you can claim
If closing or occupancy happens after the firm date, or you end the agreement because of delay, Tarion’s published rules provide:
- Living expenses at a fixed $150 a day for each day of delay, with no receipts required.
- Other costs caused by the delay, such as extra moving or storage, with receipts.
- A maximum of $7,500 in total delay compensation under the warranty.
If you end the agreement because of delay, you are also entitled to a full refund of all money paid, including deposits, extras and upgrades, plus interest.
When the builder can delay without paying
The addendum allows extensions for “unavoidable delays,” such as strikes or natural disasters. The builder must tell you when the unavoidable delay starts, estimate how long it will last, and give written notice when it ends. Dates can then be extended without delay compensation. A builder may also move dates by mutual written agreement, so read anything you are asked to sign carefully before agreeing to a new date.
Your right to end the agreement
If the home is not complete by the Outside Closing Date or Outside Occupancy Date, you have a 30-day Purchaser’s Termination Period during which you can end the agreement. For a condo, this is separate from the 10-day cooling-off period that applies right after you sign. Talk to your lawyer before you act, because ending an agreement has consequences for your financing and your plans.
How to claim
Make your claim to the builder first, within 180 days of your closing or occupancy date (or of the date you ended the agreement). If the builder does not pay or you cannot agree on the amount, you can claim to Tarion during the first year of possession, or within 365 days after ending the agreement, using the delayed closing or occupancy claim form in Tarion’s MyHome portal.
A hypothetical example
Here is an illustration only, not a real case: a freehold buyer’s firm closing date is missed and the builder sets a delayed closing date 20 days later, with proper notice. Using the $150 daily rate, living-expense compensation would be 20 x $150 = $3,000, plus any receipted extra moving or storage costs, all within the $7,500 cap. If the builder had given less than 10 days’ notice of the delay, the $1,500 short-notice payment would also be relevant. Your lawyer can confirm how the rules apply to your agreement.
Frequently asked questions
Can a builder delay my closing as many times as it wants?
No. Delays must follow the notice rules and stay within the dates in the Statement of Critical Dates. Past the outside date, you gain a right to end the agreement.
Is delay compensation the same for condos and freehold homes?
Tarion describes the same $150 daily living-expense rate and $7,500 maximum for delayed closing on freehold homes and delayed occupancy on condo units, though the date structure differs.
Do I need receipts for hotel or rent costs?
Not for the fixed $150 daily living-expense amount. Receipts are required for other delay costs such as moving and storage.
Where can I check the current rules?
Tarion publishes the delayed closing and delayed occupancy rules on tarion.com, and your agreement’s addendum is the document that applies to you.
Plan around the dates
Critical dates affect your rent or lease, your mortgage approval and the sale of any home you own now. We walk buyers through the Statement of Critical Dates before they sign, and our service is free for buyers. Call or text 905-274-3000, register for VIP access, or read our Tarion warranty guide for the rest of your protections.